Lostock Electrical Projects have provided services for many high profile customers. Below is just a small selection of our most recently completed projects.

Installation of a fully automated Motor Control Center for Harry Carr Ltd of Grimsby. This project, completed during 2004, was built to exact customer specifications and was designed to provide control over a cold storage plant.
This contract was valued at £100,000

Throughout 2003 and 2004 we installed power factor correction capacitors and controls for United Utilities at a large number of sites. These contracts were valued at £250,000

In 2003 we delivered a 100KVA Package Sub Station for the Whitehaven call centre of Cegelec PLC. This contract was valued at £54,000

In 2004 we supplied a Mains and Generator Switchboard and Motor Control Centres for Biwater as part of the update of United Utilities Watchgate water treatment works. This contract was valued at £1.1 million

We have recently completed the installation of Mains Switchboards and Subsidiary Distribution Boards for John Lewis Stores at Cheadle, Bluewater and Bristol.

We have installed Automatic Changeover Switchboards at Nottingham Hospital. This contract was valued at £90,000.